 3rd & 4th segment

 


Summary maps and visualisations of the Segments 3 and 4

Layout
Detailed description of the layout
Advantages and disadvantages of the chosen General Option
Main technical parameters
Opinion of society
Substantiation for choice of the General Option
Real estate
Costs
Results of economic assessment
Chronology of designing works

Layout

The approved General Option of layout of the Segments 3 and 4 of the Riga Northern Transport Corridor starts at Daugavgriva street and ends in the designed road junction at Priedaine where connection of motor road Riga – Ventspils and the Northern Corridor is planned. Route of the Segment 3 of the Northern Corridor goes along the administrative territory of the Riga city while the Segment 4 crosses administrative territories of Babite and Jurmala.

Substantiation for choice of the General Option is available here.

Detailed description of the layout

The western part of the route of the chosen General Option of the Segments 3 and 4 of the Northern Corridor goes along the existing motor road A10 (highway Riga – Jurmala) until road junction with motor road A5 (Salaspils – Babite, Riga bypass). The chosen General Option does not plan reconstruction of the highway Riga – Jurmala until road junction of motor roads A5 and A10; meanwhile, rebuilding of road junction of existing motor roads A5 and A10 is included in the project.
In the road junction of motor roads A5/A10, the route turns towards Babite, crosses railway Riga – Tukums, and moves on along the existing motor road A5 up to its turn to Babite. Here is planned a road junction of the new route and the motor road A5. This span of the motor road A5 is going to be slightly expanded.
Then the route of the Northern Corridor continues in the territory of Babite region through a new-built route towards Saulisciems parish. Here the route is placed between sludge fields of the water treatment plant “Daugavgriva” and Hapaka trench. Further in east the route moves through natural territories of the Jurmala city (mainly forests) in order to recess it as far as possible away from existing and perspective buildings.
In the territory of the Riga city, the route is located in limits of red lines granted to it: it crosses Spilve polder meadows north of Kleisti. Northern Corridor shall be connected with Kleistu street by a multilevel crossing. Further in east, the route will have a two-level crossing over railway Zasulauks – Bolderaja located about 500 m east, in territory of Ratsupe allotments where the Segment 3 ends and the Segment 2 of the Northern Corridor starts. 

Advantages and disadvantages of the chosen General Option

Advantages

Disadvantages

  • comparatively smallest adverse impact on inhabitants, institutions, and buildings in neighbourhood of the planned motor road during period both of construction and exploitation of the object
  • major public support
  • highest results in assessment of experts
  • demolition of not a single building is needed
  • crosses the smallest amount of real estates
  • conforms to territorial plans of all involved municipalities
  • comparatively high construction costs
  • in several spans (Spilve meadows and territory of pump station of Spilve polder), the route crosses territories with extremely construction-inappropriate conditions (hydrology and geology) that require voluminous work on preparation of engineering technologies

 

Main technical parameters

 

General Option

Road category

High-speed motor road of category A1 and street of the Riga city of category B

Road function

Main connection. To provide communication between main centres of the state (in span of motor road of category A1)
To receive traffic flows from city suburbs and transit and bring them to external network of highways and mains (in span of street of category B)

Calculated and designed speed, km/h

110

Total length of the route, km

14.400

Length of route spans to be built new, km

10.691

Length of network of local roads (except road junctions), km

4.87

Planned amount of road junctions

3

Forecasted traffic intensity in 2041
(scenario 3 or 3b), veh./24h

Section 1

55 528

Section 2

61 276

Section 3

56 145

Section 4

56 145

Section 5

74 687

Forecasted width of motor road and amount of driving lines

Section 1

32, 3+3 (existing span of motor road A10 Priedaine – Babite)

Section 2

NP29.5, 2+2

Section 3

NP29.5, 2+2

Section 4

NP35.5, 2+2

Section 5

NP33, 3+3

Impact on traffic flow and safety in the Riga city and its neighbourhood

It will considerably improve the traffic flow and reduce amount of RTAs in the existing network of roads and streets.

 

Impact on traffic organization in territories adjacent to the route

Improved organization of the local traffic and improved access to mains and highways is forecasted; access to all real estates will be provided

Organization of flow of pedestrians and bicyclists

Along streets and roads of local significance, over pedestrians’ bridges and through tunnels

Organization of flow of public transport

Low-speed public transport: along streets and roads of local significance; high-speed public transport: also along basic route without stops on the basic route 

Impact on landscape quality

Quality of natural landscapes will decrease; quality of degraded landscapes will improve

Impact on cultural monuments

Crosses buildings of Kleisti manor and protective zone of potential cultural monument – battle places of the Latvia liberation war at houses of Viki tavern.
Monuments are not affected.

Places that are technologically complicated for execution of construction works

Crossing of meliorated Spilve meadows and Hapaka trench at pump station of Spilve polder

Public support (following results of public discussion of the working report of the EIA)

Supported by main part of society (88.7%)

Opinion of society

In the period from May 7 to June 7, 2010, working report on the EIA developed by „Eiroprojekts” SIA was delivered for public discussion; the working report was based on decision taken by the Environment State Bureau on July 4, 2007.

During public discussion, three meetings in Riga, Jurmala, and the Babite region were organized; in addition, inhabitants had possibility to fill-in and to submit written reference questionnaires.

Process of social discussion presented a very active participation of society:

  • 3 meetings of public discussion were attended by 117 participants;
  • 12 letters, several informative phone calls and e-mails were received;
  • 406 reference questionnaires were received.

Written proposals included sound support to the offered 2nd Option (88.7% of respondents).

360 balsis – par 2. variantu – 360 votes for the 2nd Option
12 balsis – par 2a. variantu – 12votes for the Option 2a
2 balsis – par 3. variantu – 2 votes for the 3rd Option
28 balsis – nav norādīts – 28 votes – not defined
4 balsis – par 1. variantu – 4 votes for the 1st Option

More detailed information on results of abovementioned public discussions is available here.

Substantiation for choice of the General Option

In order to take a substantiated decision on the General Option of the Segments 3 and 4 of the Northern Corridor, three alternative options of layout were offered to society and authorities for evaluation that are available here.

On June 25, 2007, the City Development Department of the Riga City Council submitted to the Environment State Bureau an application on designing of the Segments 3 and 4 of the Northern Corridor.
On July 4, 2007, decision on application of environment impact assessment (further in the text referred as the EIA) for the planned construction of highway in span from crossing of motor roads A5 and A10 until Daugavgrivas street was taken.

In the period from July 16 to August 20, 2007, initial public discussion on the EIA along with public discussion of the construction initiative carried on.

On October 29, 2007, the Environment State Bureau issued an EIA program.

In the period from May 7 to June 7, 2010, public discussion on the working report of the EIA on the Segments 3 and 4 of the Northern Corridor went on. In scope of public discussion, three meetings in Riga (in the council of the Riga city), Jurmala (in the council of the Jurmala city), and the Babite region (in hall of the Babite high school) were organized. 3 technical solutions of the route were offered for public discussion; in the territory of the Riga city, subversion of the 2nd Option was offered as well.

On January 17, 2011, the Environment State Bureau issued statement on options of route layout included in the final EIA report on the Segments 3 and 4 of the Northern Corridor. In accordance with the statement, excluding aspects in respect of environment were not found in any of offered options.

The designer of the route of the Segments 3 and 4 of the Northern Corridor „Ceļuprojekts” AS recommended developing of the 2nd Option of the route layout as the General Option. As main advantage of this option of the layout its comparatively small impact on inhabitants and buildings of neighbourhood of the Segments 3 and 4 of the Northern Corridor was mentioned.

Decision of the Technical Committee of the Latvian State Roads coincided with recommendations of the route designer „Ceļuprojekts” AS, namely, to accept the offered 2nd Option of the route.

In addition, inhabitants supported the 2nd Option of the route layout (88.7% of 406 reference questionnaires).

On January 26, 2011, the municipality council of the Babite region and on January 27, 2011 the council of the Jurmala city decided to support further development of construction project of the 2nd Option. The Riga City Council took an equivalent decision on March 1, 2011; and it forecasted further development of the same construction project of the 2nd Option. It means that all 3 local municipalities involved in the project have a unified vision of the optimal layout of the planned route and development of the project may continue in amount of complete sketch design.

Decisions taken by the Riga City Council, Babite council, and Jurmala council are available here.

Real estate

General Option

Area of real estates to be expropriated, ha

GRAND TOTAL

132.6

In the Jurmala city

24.4

In the Babite region

38.0

In the Riga city

70.2

Area of forests to be expropriated (cut), ha

GRAND TOTAL

41.1

In the Jurmala city

12.5

In the Babite region

16.9

In the Riga city

11.7

Total amount of land properties to be expropriated (estates of physical persons + legal persons + state + municipalities), pcs

GRAND TOTAL

130

In the Jurmala city

5

In the Babite region

99

In the Riga city

26

Amount of buildings to be demolished, pcs

GRAND TOTAL

0

In the Jurmala city

0

In the Babite region

0

In the Riga city

0

Amount of dwelling houses to be demolished, pcs

GRAND TOTAL

0

In the Jurmala city

0

In the Babite region

0

In the Riga city

0

Summary evaluation of factors affecting the environment is available here

Costs

Cost calculations performed by „Ceļuprojekts” AS with prices of the year 2009*, mio LVL, without VAT

 

General Option

Costs of project effectuation **

174.216

Costs for obtaining of real estates

2.529

Exploitation costs of motor roads and bridges***

47.567

* - construction costs are calculated in accordance with market conditions in Latvia following prices of the year 2009. However, costs (for example, overhead expenses, profit) temporary reduced by construction companies due to the current conditions of economic and financial downturn are included. Costs will be specified in course of further development of the project;
** - costs of project effectuation include costs for construction, obtaining of real estates, designing work, building supervision, unexpected construction works, and author supervision;
*** exploitation costs are offered for a 27-year period, which is the period of economic calculations (for years 2015 – 2041).


Results of economic assessment

 

General Option

Current net value of the project (NPV), mio LVL

175.440

Ratio of gains – losses

2.28

Rate of the project internal profit (IRR)*, %

18.97

* - general economic calculations show that project is economically efficient if IRR>8%.

Chronology of designing works

  • July 16 – August 20, 2007: initial public discussion on the EIA of the planned construction of the Segments 3 and 4 of the Northern Corridor along with public discussion of the construction initiative carried on.
  • October 17, 2007: the municipality council of the Babite region takes decision accepting the construction initiative.
  • October 23, 2007: the Riga City Council takes decision accepting the construction initiative.
  • December 20, 2007: the council of the Jurmala city takes decision accepting the construction initiative.
  • July 29, 2009: contract with „Ceļuprojekts” AS on development of sketch design and EIA for the Segments 3 and 4 of the Northern Corridor is concluded.
  • May 07 – June 07, 2010: public discussion on the working report on the EIA.
  • January 17, 2011: procedure of EIA concludes with statement of the Environment State Bureau issued on the prepared final report on EIA of the Segments 3 and 4 of the Northern Corridor.
  • January 26, 2011: the municipality council of the Babite region takes decision to support the 2nd Option of the Segments 3 and 4 of the Northern Corridor.
  • January 27, 2011: the council of the Jurmala city takes decision to support the 2nd Option of the Segments 3 and 4 of the Northern Corridor.
  • March 01, 2011: the Riga City Council takes decision on the General Option of the Segments 3 and 4 of the Northern Corridor (the 2nd Option). Basing on this decision, the sketch project will be developed for the 2nd Option.

 